Multiple Choice
Under a standard cost system,who is usually held responsible for the materials price variances?
A) The production manager.
B) The sales manager.
C) The purchasing manager.
D) The engineering manager.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q200: (Appendix 10B)The following is the standard
Q201: Purchase of poor quality materials will generally
Q202: The Alpha Company produces toys for national
Q203: A favourable labour efficiency variance would
Q204: Cole Laboratories makes and sells a
Q206: Which of the following is directly associated
Q207: For the month of April,Thorp Co.'s
Q208: One cause of an unfavourable overhead volume
Q209: At Jacobson Company,indirect labour is a variable
Q210: Bryan Company employs a standard