 The following labour standards have been established for a particular product:  Standard labour hours per unit of output 7.5 hours  Standard labour rate $15.25 per hour \begin{array}{l}\text { The following labour standards have been established for a particular product: }\\\begin{array} { | l | r | } \hline \text { Standard labour hours per unit of output } & 7.5 \text { hours } \\\hline \text { Standard labour rate } & \$ 15.25 \text { per hour } \\\hline\end{array}\end{array}
 The following data pertain to operations concerning the product for the last month:  Actual hours worked 9,600 hours  Actual total labour cost $144,480 Actual output 1,200 units \begin{array}{l}\text { The following data pertain to operations concerning the product for the last month: }\\\begin{array} { | l | r | } \hline \text { Actual hours worked } & 9,600 \text { hours } \\\hline \text { Actual total labour cost } & \$ 144,480 \\\hline \text { Actual output } & 1,200 \text { units } \\\hline\end{array}\end{array}
-What was the labour rate variance for the month?


A) $240 favourable.
B) $240 unfavourable.
C) $1,920 favourable.
D) $1,920 unfavourable.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions