Multiple Choice
Which of the following variances is caused by a difference between the denominator activity in the predetermined overhead rate and the standard hours allowed for the actual production of the period?
A) Variable overhead spending variance.
B) Variable overhead efficiency variance.
C) Fixed overhead budget variance.
D) Fixed overhead volume variance.
Correct Answer:

Verified