Multiple Choice
Petroleum Inc. (PI) controls off-shore oil leases. It is considering the construction of a deep-sea oil rig at a cost of $500 million. The price of oil is $100/bbl. and extraction costs are $50/bbl. PI expects costs to remain constant. The rig will produce an estimated 1,200,000 bbl. per year forever. The risk-free rate is 10 percent per year, which is also the cost of capital. (Ignore taxes) . Suppose that oil prices are uncertain and are equally likely to be $120/bbl. or $80/bbl. next year. Suppose that PI has the option to postpone the project by one year. Calculate the value of the real option to postpone the project for one year. (There is some rounding in the answer.)
A) +$30 million
B) +$50 million
C) +$54 million
D) +$70 million
Correct Answer:

Verified
Correct Answer:
Verified
Q30: In constructing a Monte Carlo simulation model
Q31: Briefly explain the term real options.
Q32: Define the term abandonment value.
Q33: You are planning to produce a new
Q34: Hammer Company proposes to invest $6 million
Q36: In most cases the net present value
Q37: Briefly explain timing options.
Q38: The following are drawbacks of sensitivity analysis
Q39: A project requires an initial investment in
Q40: Briefly discuss break-even analysis.