Spruce Bank is planning to automate some of its back office functions and reduce operating costs.The installation of new computers and software will require an initial investment of $1,000,000.The savings generated because of reduced personnel cost is $200,000 per year.The bank uses an 8 percent rate of discount to evaluate cost saving projects which are expected to last 10 years.
Should the bank undertake the project given the above information?
A) Yes,because the NPV of the project is $500,000.
B) Yes,because the NPV of the project is $342,016.
C) No,because the NPV of the project is -$500,000.
D) No,because the NPV of the project is -$201,458.
Correct Answer:

Verified
Correct Answer:
Verified
Q31: New retail products and services based heavily
Q41: In the U.S., electronic methods of payment
Q48: The U.S.Treasury has recently proposed that banks
Q55: Technological efficiency focuses exclusively on the cost
Q58: Daylight overdraft risk occurs because banks often
Q68: Wholesale cash management services allow corporate customers
Q70: If AC<sub>X + Y</sub> < AC<sub>X</sub> +
Q88: In recent years, U.S.banks have alone spent
Q97: Noninterest expense has increased faster than interest
Q102: Which of the following best describes economies