Multiple Choice
Suppose a project is subject to the following risk events (each with a given probability of occurring and a cost associated with that occurrence) : Given these, Event _____ should probably get the most attention and Event _____ should probably get the least.
A) II; IV
B) III; IV
C) I; III
D) I; II
E) II; III
Correct Answer:

Verified