Multiple Choice
Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?
A) expected project duration
B) activity slack time
C) which activities are on the critical path
D) variance in project duration
E) maximum project duration
Correct Answer:

Verified
Correct Answer:
Verified
Q29: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q30: One way that project management differs from
Q31: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q32: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q33: In the probabilistic approach to project network
Q35: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q36: Slack time is equal to LS-ES or
Q37: Most likely time generally is at least
Q38: In a project network, the critical path
Q39: A method used for establishing a logical