    In the Probabilistic Approach to Project Network Analysis, the Time
Solved

In the Probabilistic Approach to Project Network Analysis, the Time

Question 33

Question 33

Multiple Choice

In the probabilistic approach to project network analysis, the time estimate annotated tm for any activity is the


A) mean time.
B) median time.
C) most likely time.
D) mode time.
E) marginal time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q28: The probability of occurrence of risk events

Q29: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q30: One way that project management differs from

Q31: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q32: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q34: Which of the following is determined as

Q35: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q36: Slack time is equal to LS-ES or

Q37: Most likely time generally is at least

Q38: In a project network, the critical path

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines