    A PERT/CPM Activity Has an Optimistic Time Estimate of Three
Solved

A PERT/CPM Activity Has an Optimistic Time Estimate of Three

Question 25

Question 25

Multiple Choice

A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is


A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q20: Gantt charts are most closely associated with<br>A)JIT.<br>B)PERT.<br>C)MRP.<br>D)MRPII.<br>E)Six

Q21: Although PERT and CPM were originally developed

Q22: A project is represented by the following

Q23: Which of the following is not a

Q24: A popular visual tool for planning and

Q26: Activities not on the critical path have

Q27: Activity J has a duration of 7

Q28: The probability of occurrence of risk events

Q29: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"

Q30: One way that project management differs from

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines