Multiple Choice
A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is
A) 7.0.
B) 7.5.
C) 8.0.
D) 8.5.
E) 10.0.
Correct Answer:

Verified
Correct Answer:
Verified