Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Activity E
Multiple Choice
Consider the following work breakdown structure: What is the estimated expected (mean) time for activity E?
A) 31 weeks
B) 38 weeks
C) 39 weeks
D) 40 weeks
E) 43 weeks