Solved

Consider the Following Work Breakdown Structure What Is the Probability That the Critical Path for This

Question 91

Multiple Choice

Consider the following work breakdown structure:  Duration Estimates (Days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  U, V  U  W 355065 V  W, X 284052 W  Z 263544 X  Y 284052 Y  Z 262938 Z  End 366084\begin{array}{r}\text { Duration Estimates (Days) }\quad\quad\quad\\\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { U, V } & - & - & - \\\text { U } & \text { W } & 35 & 50 & 65 \\\text { V } & \text { W, X } & 28 & 40 & 52 \\\text { W } & \text { Z } & 26 & 35 & 44 \\\text { X } & \text { Y } & 28 & 40 & 52 \\\text { Y } & \text { Z } & 26 & 29 & 38 \\\text { Z } & \text { End } & 36 & 60 & 84\end{array}\end{array} What is the probability that the critical path for this project will be completed within 200 days?


A) 0.8413
B) 0.9544
C) 0.9772
D) 0.9974
E) 0.9987

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions