Multiple Choice
Which of the following leads to simulation being a useful tool with uncertain activity times?
A) paths that are not independent
B) activity times that are not deterministic
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates
Correct Answer:

Verified
Correct Answer:
Verified