The Owner/operator of the Local Franchise of Handyman, Inc If He Uses the First Come, First Served Priority Rule
Multiple Choice
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?
A) 7.5 hours
B) 5 hours
C) 3 hours
D) 2.5 hours
E) 2 hours
Correct Answer:

Verified
Correct Answer:
Verified