The Owner/operator of the Local Franchise of Handyman, Inc If He Uses the First Come, First Served Priority Rule

Question 11

Multiple Choice

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing  Time (hrs)   Due  (hrs from now)   W 44X35Y22Z11\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \text { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?


A) 7.5 hours
B) 5 hours
C) 3 hours
D) 2.5 hours
E) 2 hours

Correct Answer: