Multiple Choice
The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows: Where in the optimum sequence should car A be scheduled?
A) first
B) second
C) third
D) fourth
E) fifth