Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):
What is the average completion time for the first come, first served priority rule schedule? Average job tardiness? Average number of jobs at the center?
Correct Answer:

Verified
11.6 days;...View Answer