    One Major Difference Between the Use of Kanban and MRP
Solved

One Major Difference Between the Use of Kanban and MRP

Question 8

Question 8

True/False

One major difference between the use of kanban and MRP in scheduling the products to be built is that kanban is primarily a manual system while MRP uses computers.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: In the lean philosophy, the larger the

Q10: The Four Star Publishing Company uses 60

Q11: The goal of lean operations is to

Q12: The ultimate objective in a lean system

Q15: Kanban is the Japanese term for autonomation.

Q38: Which of the following is not something

Q44: The small lot-sizing policy works well in

Q73: Previously, management calculated the number of kanban

Q82: Which of the following is not a

Q83: With regard to suppliers, lean systems typically

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines