Multiple Choice
Refer to this product tree: If 17 Ps are needed, and no on-hand inventory exists for any items, how many Cs will be needed?
A) 8
B) 16
C) 136
D) 204
E) 272
Correct Answer:

Verified
Correct Answer:
Verified