Multiple Choice
Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand: Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs; additionally one bottle of Alka-Seltzer is included for those who overindulge. What is the net requirement for dark chocolate truffles to fill this order?
A) 100
B) 140
C) 150
D) 180
E) 200
Correct Answer:

Verified
Correct Answer:
Verified
Q21: Lumpy demand for components results primarily from
Q25: ERP implementation probably will not require:<br>A) cross-functional
Q27: Bunny Helpers, Inc., has just received
Q29: End item Alpha's product structure tree and
Q30: Net requirements for component J are as
Q33: In MRP, under lot-for-lot ordering, planned-order receipts
Q34: The MRP input listing the assemblies, subassemblies,
Q57: In MRP, scheduled receipts are<br>A)identical to planned-order
Q71: In MRP, EOQ models tend to be
Q72: A bill of materials contains a listing