Multiple Choice
A firm has 43 units of a certain product on hand. Forecasts for the first two planning periods are 20 units each. A production quantity of 80 units is planned to be available in period 3. Customer orders are 22 for period 1 and 17 for period 2. What is the projected on-hand inventory at the end of period 2?
A) 21
B) 1
C) 12
D) 20
E) impossible to say without more information
Correct Answer:

Verified
Correct Answer:
Verified
Q10: Ultimately the overriding factor in choosing a
Q11: Aggregate planners attempt to balance<br>A)demand and inventories.<br>B)demand
Q12: Linear programming to produce an aggregate plan<br>A)will
Q13: One area in which aggregate planning decisions
Q14: Aggregate planning in the case of a
Q16: This aggregate planning technique is known for
Q17: Proactive and reactive aggregate planning strategies are
Q18: Aggregate planning is capacity planning for<br>A)the long
Q19: Accommodating peak demand and effectively using labor
Q20: Aggregate planners commonly use trial-and-error methods in