Multiple Choice
A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In a preliminary study, he observed one of his workers perform this task five times, with the following results: What is the normal time for this task if the employee worked at a 20 percent faster pace than average?
A) 16.7 seconds
B) 20 seconds
C) 24 seconds
D) 25 seconds
E) 100 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q7: The owner of Kat Motel wants
Q9: Given the following work sampling data,
Q10: Measured day work refers to an output-based
Q12: A methods and measurements analyst for
Q14: Methods analysis cannot be done for new
Q23: Many lower-level jobs are monotonous and boring.
Q49: Methods analysis is particularly valuable when it
Q95: Process chart symbols do not include:<br>A)delay.<br>B)inspection.<br>C)operation.<br>D)rejection.<br>E)storage.
Q98: Which is not a requirement for an
Q125: A methods and measurement analyst wants to