Multiple Choice
A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7 minutes. The minimum cycle time in minutes is:
A) .3.
B) .7.
C) 1.4.
D) 2.4.
E) .8.
Correct Answer:

Verified
Correct Answer:
Verified