Multiple Choice
A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: If the company wants the output rate to be equal to demand, what is the minimum number of workstations needed?
A) 3
B) 4
C) 5
D) 6
E) 7
Correct Answer:

Verified
Correct Answer:
Verified