Multiple Choice
All of the following are examples of Facility-level costs except:
A) Costs of cleaning the workplace.
B) Costs of custodial work.
C) Costs of personnel support.
D) Costs of receiving shipments.
E) Costs of providing electricity.
Correct Answer:

Verified
Correct Answer:
Verified