Essay
Jester Corporation, which has a maximum labour capacity of 30,000 hours per month, has considerable flexibility with its customers when it comes to project completion dates. Management is considering the submission of a bid for a job to be performed for the city of Cambridge, Ontario. Costs for the job are as follows: Jester's labour force is paid an average of $22 per hour and if the company wins the bid, it will have three months to complete the work. Management adds a 30% profit margin to all jobs, computed on the basis of total variable cost.
Required:
A. Compute the lowest total cost that the company would use when figuring its bid, assuming that Jester has excess capacity.
B. Compute Jester's bid if the company has no excess capacity.
C. Assume that Jester is currently working at 85% of capacity. Does the firm have sufficient time to complete the job? If not, what could the company do if it desires to do business with the city of Cambridge?
Correct Answer:

Verified
A. The lowest total cost is the variable...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: Kendrick Corporation sells a single product. The
Q6: Heathrow employs cost-plus pricing formulas to derive
Q7: Which of the following formulas represents the
Q9: The curve that shows the relationship between
Q11: If a company has excess capacity, which
Q12: The following costs relate to JB Contraction
Q13: Patterson and Clay Companies both use cost-plus
Q14: Jensen Marine Supplies Inc. uses time
Q38: Which of the following terms describes a
Q50: When determining the markup to be used