Multiple Choice
If you are going to develop an "R" chart based on range statistics and you are using a sample size of 9 for your charting purposes.Which of the following is the lower control limit D3 factor for the chart?
A) 0.08
B) 0.14
C) 0.18
D) 0.22
E) 0.29
Correct Answer: