Multiple Choice
According to Little's law,which of the following can be used to estimate work-in-process inventory?
A) Process time/Cycle time
B) Throughput rate times throughput time
C) Process velocity/Throughput time
D) Set up time/Throughput rate
E) Value added time/Process velocity
Correct Answer:

Verified
Correct Answer:
Verified