True/False
The unit improvement factor for a 60% learning curve at 25 units is 0.0933.The first and second timings of a person doing a job are 5 minutes and 3 minutes respectively.The learning-adjusted time estimate for the unit number 25 is 0.0933 minutes.
Correct Answer:

Verified
Correct Answer:
Verified