Multiple Choice
The 50th repetition of a job is timed at 100 minutes. If the learning curve for this job is 90 percent, what is the estimated time for the 200th repetition of this job?
A) 44.69 minutes
B) 81 minutes
C) 90 minutes
D) 100 minutes
E) 110 minutes
Correct Answer:

Verified
Correct Answer:
Verified