Multiple Choice
At the 10th repetition of job it is timed at 100 minutes.If the learning curve for this job is 80 percent,what is the estimated time for the 100th repetition of this job?
A) 47.65 minutes
B) 62.50 minutes
C) 80 minutes
D) 92.50 minutes
E) 100 minutes
Correct Answer:

Verified
Correct Answer:
Verified