    The 15<sup>th</sup> Repetition of a Job Is Timed at 100
Solved

The 15th Repetition of a Job Is Timed at 100

Question 3

Question 3

Short Answer

The 15th repetition of a job is timed at 100 minutes.If the learning curve for this job is 90 percent,what is the estimated time for the 120th repetition of this job?

Correct Answer:

verifed

Verified

Related Questions

Q6: The unit improvement factor is not as

Q8: Learning curves only estimate the learning rates

Q9: If a person performing a task has

Q11: You have just timed a person doing

Q14: An assumption of learning curve theory is

Q17: A learning curve is a line displaying

Q26: If a person performing a task has

Q28: You have determined that a 60 percent

Q39: Which of the following computational methods are

Q46: An assumption of learning curves is that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines