Multiple Choice
The engineering team of Beta Co. ,is in the process of developing an action map based on selected alternatives.The team is working on:
A) the "plan" step of the PDCA cycle.
B) the "do" step of the PDCA cycle.
C) the "check" step of the PDCA cycle.
D) the "act" step of the PDCA cycle.
Correct Answer:

Verified
Correct Answer:
Verified