What is the best approach to take into account the relative risk of a proposed project?


A) adjusting the discount rate upward if the project is judged to have above-average risk
B) reducing the NPV by 10% for risky projects
C) picking a risk factor equal to the average discount rate
D) ignoring risk because project risk cannot be measured accurately