Which of the Following Is Not a Criterion in Favor

Question 12

Multiple Choice

Which of the following is not a criterion in favor of using cost-type arrangements?


A) Research and development increases technical risk
B) Project completion is in doubt
C) Product specifications are incomplete
D) Delivery times are certain
E) High-dollar, highly uncertain procurements are involved

Correct Answer: