Instead of Completing One Task Before Starting Another,Perry's Team Begins

Question 80

Multiple Choice

Instead of completing one task before starting another,Perry's team begins each task as soon as possible,allowing tasks to overlap where possible.Perry's team is using


A) a self-managing team.
B) a sequential process.
C) TQM.
D) customization.
E) a partly parallel process.

Correct Answer: