Multiple Choice
You are analyzing a project and have prepared the following data: Required payback period: 2.5 years
Required AAR: 7.25%
Required return: 8.50%
Based on the payback period of _____for this project,you should _____ the project.
A) 1.87 years; accept
B) 2.87 years; accept
C) 2.87 years; reject
D) 3.13 years; reject
E) 3.87 years; reject
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The internal rate of return (IRR): I.