Multiple Choice
Given the portion of the network shown above,what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 23?
A) 3.
B) 4.
C) 9.
D) 10.
E) 12.
Correct Answer:

Verified
Correct Answer:
Verified