Multiple Choice
The purpose of performing a forward pass is to:
A) Identify the critical path
B) Determine the early start and the early finish times
C) Determine the late start and the late finish times
D) Determine the slack available in the process
Correct Answer:

Verified
Correct Answer:
Verified