A bottleneck is:
A) A resource that has the maximum capacity in the facility
B) A resource whose capacity is less than the capacity of all other resources and whose capacity is less than the demand placed on it
C) A resource that blocks labor productivity
D) A resource that has the fastest processing time
Correct Answer: