Multiple Choice
Which of the following statements is NOT true about finite capacity scheduling (FCS) ?
A) FCS is an extension of Gantt chart methods.
B) FCS requires that jobs are loaded backward from due dates to determine the capacity required at each work center.
C) FCS assumes that jobs are scheduled through a number of work centers,each with one or more machines.
D) In FCS,attention is paid to scarce resources to facilitate job flow and to improve the performance of the shop.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Which of the following statements is NOT
Q15: Which of the following is NOT determined
Q16: Optimal sequencing rules have found widespread use
Q17: Lead time for completion of a job
Q20: The reason(s)for batch scheduling being a complex
Q21: The Shortest process time (SPT)rule is better
Q24: According to Goldratt:<br>A)An hour lost at the
Q25: Finite Capacity Scheduling can be used to
Q26: Which of the following is a performance
Q38: Scheduling deals with which three conflicting objectives?<br>A)