    Exam 7: Project Cost Management
  5. Question
    If Cost Variance Is a Positive Number,it Means That Performing
Solved

If Cost Variance Is a Positive Number,it Means That Performing

Question 13

Question 13

True/False

If cost variance is a positive number,it means that performing the work cost more than planned.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: List and describe the three values calculated

Q9: The people who develop software cost estimates

Q10: Many organizations now collect and control an

Q11: _ considers the total cost of ownership,or

Q12: Information technology project managers need to be

Q14: If a project manager gets sick for

Q15: When deciding what projects to invest in

Q16: _ is a method for determining the

Q17: If the cost estimate will be the

Q18: _ should be forgotten.<br>A)Sunk costs<br>B)Indirect costs<br>C)Direct costs<br>D)Intangible

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines