Multiple Choice
____ use the actual cost of a previous,similar project as the basis for estimating the cost of the current project.
A) Actual estimates
B) Parametric estimates
C) Bottom-up estimates
D) Analogous estimates
Correct Answer:

Verified
Correct Answer:
Verified