____ Involve Estimating Individual Work Items or Activities and Summing

Question 39

Multiple Choice

____ involve estimating individual work items or activities and summing them to get a project total.


A) Actual estimates
B) Parametric estimates
C) Bottom-up estimates
D) Analogous estimates