Multiple Choice
The goal of ____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.
A) defining activities
B) sequencing activities
C) estimating activity resources
D) estimating activity durations
Correct Answer:

Verified
Correct Answer:
Verified