____ dependencies are inherent in the nature of the work being performed on a project.


A) Mandatory
B) Discretionary
C) External
D) Internal

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q26:  In a(n) _ relationship, the "from" activity

Q67: In a network diagram,a(n)_ is simply the

Q68: _ results in supporting detail to document

Q69: _ involves evaluating the reasons for dependencies

Q70: Project managers must use discipline to control

Q72: _ dependencies are sometimes referred to as

Q73: Managers like to see progress made on

Q74: One of the first reality checks on

Q75: A _ is a hierarchical structure that

Q76: Individual work styles and cultural differences may

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines