The Ultimate Goal of ____ Is to Create a Realistic

Question 53

Multiple Choice

The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project.


A) defining activities
B) sequencing activities
C) developing the schedule
D) estimating activity duration

Correct Answer: