____ Involves Reviewing the Project Charter,requirements Documents,and Organizational Process Assets

Question 61

Multiple Choice

____ involves reviewing the project charter,requirements documents,and organizational process assets to create a scope statement,adding more information as requirements are developed and change requests are approved.


A) Planning scope
B) Defining scope
C) Controlling scope
D) Verifying scope

Correct Answer: