Multiple Choice
____ involves working with stakeholders to create the document that formally authorizes a project.
A) Developing the project charter
B) Developing the preliminary project scope statement
C) Developing the project management plan
D) Directing and managing project execution
Correct Answer:

Verified
Correct Answer: