Multiple Choice
____ include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs.
A) Initiating processes
B) Planning processes
C) Executing processes
D) Monitoring and controlling processes
Correct Answer:

Verified
Correct Answer:
Verified