    In the ____ Phase,the Project Team Creates More Detailed Project
Solved

In the ____ Phase,the Project Team Creates More Detailed Project

Question 8

Question 8

Multiple Choice

In the ____ phase,the project team creates more detailed project plans,a more accurate cost estimate,and a more thorough WBS.


A) development
B) implementation
C) concept
D) close-out

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3: _ is a set of shared assumptions,values,and

Q4: Most IT projects involve a major amount

Q5: Many companies have realized that information technology

Q9: In early phases of a project life

Q10: Project organizations may miss economies of scale

Q13: _ is a problem-solving approach that requires

Q18:  The three spheres of systems management are

Q27:  In a(n) _ organizational structure, project managers

Q37: The _ characteristic of organizational culture describes

Q85:  Describe each of the three major types

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines