Multiple Choice
____ are developed for risks that have a high impact on meeting project objectives,and are put into effect if attempts to reduce the risk are not effective.
A) Fallback plans
B) Contingency reserves
C) Contingency plans
D) Contingency allowances
Correct Answer:

Verified
Correct Answer:
Verified